Current Construction Activities Update
2025 Sewer Rehab Project
Project has begun- work in the Tiburon service area has been completed- work currently underway in the Belvedere service area near or on Belvedere Ave- (White Trucks/Green Lettering - APB Engineering).
Belvedere Ave to be closed on 8/22 for sewer pipe line rehabilitation from our Contractor APB
Main Plant Digester Cleaning and Rehabilitation Project
Project has begun - project is over 50% complete -continued grinding and sandblasting noise operations will be on-going from 8/18 through 8/29. We understand the project noise is a nuisance not only to the neighboring community but also to staff. Rest assured that this type of operation only occurs every once every 10-15 years. This required rehabilitation will ensure the continued safe, reliable and efficient operation our community has come to expect from SD5.