2022 Sewer Rehabilitation Project Completed

May contain: road, tarmac, helmet, adult, male, man, person, clothing, glove, plant, footwear, and shoe

The 2022 Sewer Rehabilitation Project is comprised of the rehabilitation of approximately 5,140 linear feet of deteriorated six-inch diameter sewer located in the Town of Tiburon and the City of Belvedere under the base bid. The pipe will be rehabilitated via pipe bursting, which will minimize disturbance to residential backyards where the sewer is located in easements.  Actual construction is planned to begin in late September 2022, prior to the wet weather season. The engineer’s cost estimate for the project was $1,417,649 for the base bid of 5,140 linear ft. of pipe rehabilitation.

 

Bids were advertised on July 22, 2022 and due on August 11, 2022.  Public notice was also published in various online plan rooms.  

Project Cost: $1,216,204

Contractor: Hardiman Construction

Year Completed: 2023